★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PRINCE2-Foundation Exam Dumps (PDF & VCE):
Available on: https://www.certleader.com/PRINCE2-Foundation-dumps.html


It is more faster and easier to pass the PRINCE2-Exams PRINCE2-Foundation exam by using Refined PRINCE2-Exams PRINCE2 Foundation exam questuins and answers. Immediate access to the Renewal PRINCE2-Foundation Exam and find the same core area PRINCE2-Foundation questions with professionally verified answers, then PASS your exam with a high score now.

2021 Oct prince2 foundation exam aberdeen:

Q71. - (Topic 2) 

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system? 

A. Corporate group 

B. Project Board 

C. Project Assurance 

D. Executive 

Answer:


Q72. - (Topic 1) 

Which is a typical core activity within configuration management? 

A. Quality assurance 

B. Risk management 

C. Verification and audit 

D. Progress reporting 

Answer:


Q73. - (Topic 2) 

Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project. 

A. Management strategies 

B. Plan 

C. Stakeholder interests 

D. Time-driven controls 

Answer:


Q74. - (Topic 2) 

Which of the following statements about customer's quality expectations and acceptance criteria are true? 

1. 

Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders. 

2. 

Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements. 

A. Only 1 is true 

B. Only 2 is true 

C. Both 1 and 2 are true 

D. Neither 1 or 2 are true 

Answer:


Q75. - (Topic 1) 

What needs to be in place to ensure effective issue and change control? 

A. Configuration management system 

B. Manage by exception 

C. Quality planning 

D. Information needs for stakeholders 

Answer:


Down to date prince2 foundation examination questions:

Q76. - (Topic 2) 

Which is a task of product-based planning? 

A. Identify activities and dependencies 

B. Write the Project Product Description 

C. Prepare the Work Packages 

D. Produce Product Status Accounts 

Answer:


Q77. - (Topic 1) 

Which is a benefit of using PRINCE2? 

A. Enables the management of projects as well as of 'business as usual' activities 

B. Can be tailored by leaving out elements of the method for some projects 

C. Can be applied to any type of project 

D. Avoids the need to involve corporate or programme management 

Answer:


Q78. - (Topic 2) 

Which document should record the agreed amount of risk budget for a project? 

A. Project Brief 

B. Project Plan 

C. Risk Management Strategy 

D. Risk Register 

Answer:


Q79. - (Topic 1) 

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances? 

A. Directing a Project 

B. Controlling a Stage 

C. Managing a Stage Boundary 

D. Managing Product Delivery 

Answer:


Q80. - (Topic 2) 

Which is a purpose of a Lessons Log? 

A. Note any lessons that are raised in Checkpoint Reports 

B. Record that corrective action is being taken 

C. Escalate lessons to the Project Board 

D. Raise improvements with Project Assurance 

Answer: