Want to know Ucertify PRINCE2-Foundation Exam practice test features? Want to lear more about PRINCE2-Exams PRINCE2 Foundation exam certification experience? Study Downloadable PRINCE2-Exams PRINCE2-Foundation answers to Improve PRINCE2-Foundation questions at Ucertify. Gat a success with an absolute guarantee to pass PRINCE2-Exams PRINCE2-Foundation (PRINCE2 Foundation exam) test on your first attempt.

2021 Jul prince2 exam foundation:

Q1. - (Topic 2) 

How many tasks does the product-based planning technique describe? 

A. One 

B. Two 

C. Three 

D. Four 

Answer: D 


Q2. - (Topic 2) 

Which statement about the quality review technique is FALSE? 

A. It enables a check to be made on a product's fitness for purpose 

B. It defines the quality responsibilities of the project team 

C. It supports the management of future changes by providing a baseline for a product 

D. It is used to gain wider acceptance of a product by involving key interested parties 

Answer: B 


Q3. - (Topic 1) 

Which is an objective of the Directing a Project process? 

A. Create and authorize the project mandate 

B. Provide management control and direction 

C. Control the day-to-day running of the project 

D. Provide accurate progress information to the Project Manager 

Answer: B 

44. - (Topic 1) 

Which process is triggered towards the end of the final stage when all the assigned work has been completed? 

A. Managing a Stage Boundary 

B. Managing Product Delivery 

C. Closing a Project 

D. Controlling a Stage 

Answer: C 


Q4. - (Topic 2) 

Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project? 

A. Managing Product Delivery 

B. Initiating a Project 

C. Managing a Stage Boundary 

D. Starting up a Project 

Answer: D 


Q5. - (Topic 1) 

Which is a purpose of the Controlling a Stage process? 

A. Assign work to be done and take corrective action to ensure that the stage remains within tolerance 

B. Provide a fixed reference point at which acceptance for the project product is confirmed 

C. Enable the Project Board to be provided with sufficient information to authorize the next stage 

D. Enable the organization to understand the work that needs to be done to deliver the project's products 

Answer: A 


PRINCE2-Foundation free exam questions

Updated prince2 foundation exam average mark:

Q6. - (Topic 2) 

Which statement applies to Stage Plans? 

A. Always have the same duration as the Project Plan 

B. Are produced at the same time as the Project Initiation Documentation 

C. Assist the Project Manager in the day-to-day running and control of the project 

D. Provide a baseline against which the Project Board monitor overall progress 

Answer: C 


Q7. - (Topic 2) 

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance? 

A. Configuration Item Record 

B. Quality Register 

C. Highlight Report 

D. Checkpoint Report 

Answer: D 


Q8. - (Topic 1) 

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken? 

A. Raise a request for change 

B. Raise an off-specification 

C. Write an Exception Report 

D. Amend the Work Package 

Answer: B 


Q9. - (Topic 2) 

Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business. 

A. controls 

B. products 

C. project management team 

D. stages 

Answer: B 


Q10. - (Topic 1) 

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment? 

A. Specify the desired result 

B. Provide the resources and skills to deliver the desired result 

C. Pay for the project 

D. Specify the benefits of the project 

Answer: B