★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions
Free Instant Download NEW PRINCE2-Foundation Exam Dumps (PDF & VCE):
Available on:
https://www.certleader.com/PRINCE2-Foundation-dumps.html
Exambible provides you the PRINCE2-Exams certification exam questions along with answers in Pdf types and Examination Engine types. After downloading along with installing these people on your PC, you can practise PRINCE2-Exams PRINCE2-Foundation test questions; evaluation your questions & answers along with check your current score. If you come across some difficulties, seek the PRINCE2-Exams PRINCE2-Foundation examine guide regarding help. Your distinctive feature is that each of our PRINCE2-Exams PRINCE2-Exams PRINCE2-Foundation on-line test serp creates a nearly true exam environment. Having PRINCE2-Exams PRINCE2-Exams online coaching is a fast and successful way to put together the PRINCE2-Exams certification exam. It is possible to through apart the lengthy PRINCE2-Exams PRINCE2-Foundation books or will not need to take other PRINCE2-Foundation courses. Studying the particular PRINCE2-Exams PRINCE2-Foundation practice materials for your own tempo and together with your own style because each of our PRINCE2-Exams test serp is flexible.Your price from the PRINCE2-Exams PRINCE2-Exams certification exam dumps is affordable. We assure you in which what you have got from Exambible is more than important. The PRINCE2-Exams PRINCE2-Foundation exam Pdf files is incredibly convenient for you personally in that they may be a quick way for the preparation from the PRINCE2-Foundation certification exam. Our objective is always to help the particular customers get the PRINCE2-Exams certification and help to make them satisfied.
2021 Dec prince2 foundation examination sample paper:
Q81. - (Topic 2)
Which of the following statements about quality assurance and Project Assurance is true?
A. Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
B. Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
C. Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
D. Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
Answer: D
Q82. - (Topic 1)
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
A. Directing a Project
B. Managing a Stage Boundary
C. Controlling a Stage
D. Starting up a Project
Answer: C
Q83. - (Topic 1)
When should the Project Board refer to corporate or programme management for a decision?
A. The stage requires resources
B. It is forecast that project level tolerance will be exceeded
C. The Senior Supplier or Senior User needs to be changed
D. Any request for change needs to be approved
Answer: B
Q84. - (Topic 1)
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2
form the [ ? ] of the method.
A. Principles
B. Themes
C. Processes
D. Techniques
Answer: A
Q85. - (Topic 2)
Which is a purpose of the Quality theme?
A. Establish how the project will ensure that all products created meet their requirements
B. Establish quality assurance to maintain the quality management system
C. Identify all the products of the project to ensure the scope has been adequately defined
D. Determine the communication needs of the organization's quality assurance function
Answer: A
Rebirth prince2 foundation examination cost:
Q86. - (Topic 1)
Which of the following statements about stakeholders are true?
1.
Someone who thinks they will be affected by a project is a stakeholder on that project.
2.
Stakeholders may be internal or external to the corporate organization.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: C
Q87. - (Topic 1)
What is the definition of a project outcome?
A. A measurable improvement that is perceived as an advantage by one or more
stakeholders
B. The reason for the project
C. The result of the change derived from using the project's outputs
D. The project's specialist products.
Answer: C
Topic 2, Volume B
Q88. - (Topic 1)
In what process is the authorization to deliver the project's products given?
A. Starting up a Project
B. Initiating a Project
C. Managing a Stage Boundary
D. Directing a Project
Answer: D
Q89. - (Topic 2)
Which is part of quality control?
A. Document the project's acceptance criteria in the Project Product Description
B. Define the quality responsibilities of those involved in the production of the products
C. Produce quality records to show that the planned quality activities have been carried out
D. Maintain the corporate organization's quality management system
Answer: C
Q90. - (Topic 1)
Which is a purpose of the Closing a Project process?
A. Authorize the final stage of the project
B. Confirm that all benefits defined in the Business Case have been achieved
C. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
D. Delegate day-to-day management of the end of the project to the Project Manager
Answer: C