With the discovering method viewpoint, numerous PRINCE2-Exams Authentication carry out any ??two within one?¡¥ technique of merging coaching business and also studying business in concert. Any lure for check draws in customers consideration and many non-computer personnel fit from it making sure that PRINCE2-Exams qualifications be a little more plus more well-liked. Nonetheless, various PRINCE2-Exams certificates create a side-effects. If your finishing pupil exposes an array of PRINCE2-Exams vouchers to your supervisor, he may obtain popularity, plus a skeptical look.
2021 Sep prince2 foundation exam average mark:
Q31. - (Topic 1)
Which should be funded from a change budget?
A. The Starting up a Project process
B. A fallback plan
C. An agreed change to the scope of a project
D. A change to a plan, within allocated tolerances, due to poor estimating
Answer: C
Q32. - (Topic 2)
Which product identifies the management stages and timescales of a project?
A. Project Brief
B. Project Product Description
C. Project Plan
D. Initiation Stage Plan
Answer: C
Q33. - (Topic 2)
Which is a true statement about time-driven controls?
A. Time-driven controls are used for monitoring the progress of Work Packages and management stages
B. Time-driven controls take place when specific events happen
C. Time-driven controls are produced at the end of a stage
D. An Exception Report is a time-driven control
Answer: A
Q34. - (Topic 1)
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
A. Off-specifications
B. Follow-on action recommendations
C. Issue Register
D. Risk Register
Answer: B
Q35. - (Topic 1)
Which does NOT reflect the PRINCE2 principle of continued business justification?
A. There must be a justifiable reason for starting a project
B. The business justification drives decision making
C. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
D. If a project can no longer be justified, it should be stopped
Answer: C
Improve prince2 foundation exam aberdeen:
Q36. - (Topic 2)
Which is a true statement about PRINCE2 event-driven controls?
A. Event-driven controls take place at predefined periodic intervals
B. Event-driven controls are produced at the frequency defined in a Work Package
C. Event-driven controls are used for decision making
D. Checkpoint Reports are event-driven controls
Answer: C
Q37. - (Topic 2)
Which describes a risk event?
A. The area of uncertainty in terms of the threat or opportunity
B. The derivation or sources of a potential risk to the project
C. The achievement of a milestone on the Project Plan
D. The sequence of events and actions that will be put in place if a risk occurs
Answer: A
Q38. - (Topic 2)
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
A. Only corporate or programme management
B. Only the Project Board
C. Only the Project Manager
D. All levels of management
Answer: D
Q39. - (Topic 1)
Which characteristic distinguishes a project from regular business operations?
A. Produces benefits
B. Introduces business change
C. Manages stakeholders
D. Incurs cost
Answer: B
Q40. - (Topic 1)
Which does the Executive need to ensure is in place before the project is initiated?
A. All Work Packages are authorized
B. An understanding of how the project will contribute to corporate objectives
C. The Project Plan has been approved
D. The Project Initiation Documentation is complete
Answer: B
38. - (Topic 1)
What is the collective name for individuals or groups who may be affected by a project?
A. Customers
B. Project Support
C. Stakeholders
D. Team members
Answer: C