Examcollection PRINCE2-Foundation PRINCE2 Foundation exam practice examination could be the best choice for you to prepare for the particular PRINCE2-Exams exam. If you wish to be considered a prominent Examcollection engineers, you cant pass by the particular Examcollection PRINCE2-Foundation PRINCE2 Foundation exam substance supply. Learn not just the actual PRINCE2-Foundation examination answers and questions and also the comprehensive reason. Transferring PRINCE2-Exams PRINCE2-Foundation accreditation is actually the first most important thing, moreover, one can learn numerous specialized knowledge and also encounters that can used in not able to practice perform.
2021 Jun prince2 foundation and practitioner groupon:
Q61. - (Topic 1)
Which is NOT one of the PRINCE2 integrated elements?
A. Tailoring PRINCE2 to the project environment
B. The processes
C. The products
D. The themes
Answer: C
Q62. - (Topic 1)
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
A. Product Description
B. Team Plan
C. Work Package
D. Stage Plan
Answer: C
Q63. - (Topic 1)
Which is a typical core activity within configuration management?
A. Issue management
B. Quality inspection
C. Identification
D. Preparation
Answer: C
Q64. - (Topic 2)
Which is NOT considered when defining risk tolerance?
A. A Project Board's attitude towards risk taking
B. The allocated risk budget
C. An organization's risk appetite
D. The amount of risk a Project Board considers acceptable
Answer: B
Q65. - (Topic 2)
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
A. Manage by stages
B. Manage by exception
C. Continued business justification
D. Learn from experience
Answer: B
Avant-garde prince2 foundation exams:
Q66. - (Topic 2)
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
A. Progress
B. Change
C. Organization
D. Quality
Answer: A
Q67. - (Topic 2)
Which is a purpose of the Risk theme?
A. Establish a method for the implementation of continuous improvement during the project
B. Identify, assess and control problems that have occurred
C. Provide the Project Board with a time-driven control to capture all project risks
D. Establish a cost-effective procedure to identify, assess and control risks
Answer: D
Q68. - (Topic 1)
Which is one of the six aspects of project performance that needs to be managed?
A. Progress
B. Change
C. Risk
D. Security
Answer: C
Q69. - (Topic 2)
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.
A. change budget
B. project budget
C. project's cost tolerance
D. project's risk tolerance
Answer: B
Q70. - (Topic 2)
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
A. Team Plan
B. Stage Plan
C. Benefits Review Plan
D. Project Plan
Answer: B