★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PMI-001 Exam Dumps (PDF & VCE):
Available on: https://www.certleader.com/PMI-001-dumps.html


To feed this kind of PMI PMI-001 examination is not a hard task. You simply have a need to consider particular calculates of accomplishing positive results. Examcollection PMI-001 qualification process content are very useful holding your current research extremely powerful or more towards symbol. We have been supplying 100% secured accomplishment inside PMI-001 real examination and also PMI-001 while using the assistance of all of our process examination. Therefore by means of training all of our PMI-001 training content, get the required qualification and try to turn into a perfect It all expert.

2021 Jan pmi-001 pdf:

Q101. A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance? 

A. -700 

B. -200 

C. 200 

D. 500 

Answer:


Q102. The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an: 

A. work package 

B. deliverable 

C. milestone 

D. activity 

Answer:


Q103. Which is one of the determining factors used to calculate CPI? 

A. EV 

B. SPI 

C. PV 

D. ETC 

Answer:


Q104. Which of the following is a tool or technique used in the Acquire Project Team process? 

A. Networking 

B. Training 

C. Negotiation 

D. Issue log 

Answer:


Q105. When would resource leveling be applied to a schedule model? 

A. Before constraints have been identified 

B. Before it has been analyzed by the critical path method 

C. After it has been analyzed by the critical path method 

D. After critical activities have been removed from the critical path 

Answer:


Replace testking pmi-001:

Q106. The component of the risk management plan that documents how risk activities will be recorded is called: 

A. tracking 

B. scoping 

C. timing 

D. defining 

Answer:


Q107. Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project? 

A. Power/influence grid 

B. Power/interest grid 

C. Influence/impact grid 

D. Salience model 

Answer:


Q108. Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation? 

A. Project 

B. Functional 

C. Program 

D. Portfolio 

Answer:


Q109. Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service? 

A. Portfolio 

B. Process 

C. Project 

D. Program 

Answer:


Q110. Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project? 

A. Analogous 

B. Parametric 

C. Bottom-up 

D. Top-down 

Answer: