Q221. Which of the following are inputs to the Plan Procurements process? 

A. Risk register, scope baseline, enterprise environmental factors, organizational process assets, project schedule 

B. Risk register, scope baseline, make-or-buy decisions, organizational process assets, project schedule 

C. Project management plan, qualified seller list, contract, enterprise environmental factors, teaming agreements 

D. Project management plan, qualified seller list, contract, make-or-buy decisions, teaming agreements 

Answer: A 


Q222. Which of the following are examples of interactive communication? 

A. Intranet sites 

B. Voice mails 

C. Video conferences 

D. Press releases 

Answer: C 


Q223. Which input provides suppliers with a clear set of goals, requirements, and outcomes? 

A. Procurement statement of work 

B. Purchase order 

C. Source selection criteria 

D. Bidder conference 

Answer: A 


Q224. An output of the Close Project (or Close Phase) process is: 

A. accepted deliverables 

B. organizational process asset updates 

C. work performance information 

D. project management plan updates 

Answer: B 


Q225. Which quality control technique illustrates the 80/20 principle? 

A. Ishikawa diagram 

B. Control chart 

C. Run chart 

D. Pareto chart 

Answer: D 


PMI-001 actual test

Up to date pmi pmi-001 practice exam:

Q226. Which is the correct formula for calculating expected activity cost for three-point estimating? 

A. Ce = (C0 + 6Cm + Cp)/4 

B. Ce = (6C0 + Cm + Cp)/4 

C. Ce = (C0 + 4Cm + Cp)/6 

D. Ce = (C0 + C., + 4Cp) / 6 

Answer: C 


Q227. What cost control technique is used to compare actual project performance to planned or expected performance? 

A. Cost aggregation 

B. Trend analysis 

C. Forecasting 

D. Variance analysis 

Answer: D 


Q228. Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process? 

A. Schedule Control 

B. Activity Definition 

C. Schedule Development 

D. Activity Resource Estimating 

Answer: D 


Q229. In the basic communication model, which term refers to the method that is used to convey the message? 

A. Decode 

B. Encode 

C. Medium 

D. Noise 

Answer: C 


Q230. Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the: 

A. Cost management plan. 

B. Work performance information. 

C. Quality management plan. 

D. Work breakdown structure. 

Answer: A