Q221. Which of the following are inputs to the Plan Procurements process?
A. Risk register, scope baseline, enterprise environmental factors, organizational process assets, project schedule
B. Risk register, scope baseline, make-or-buy decisions, organizational process assets, project schedule
C. Project management plan, qualified seller list, contract, enterprise environmental factors, teaming agreements
D. Project management plan, qualified seller list, contract, make-or-buy decisions, teaming agreements
Answer: A
Q222. Which of the following are examples of interactive communication?
A. Intranet sites
B. Voice mails
C. Video conferences
D. Press releases
Answer: C
Q223. Which input provides suppliers with a clear set of goals, requirements, and outcomes?
A. Procurement statement of work
B. Purchase order
C. Source selection criteria
D. Bidder conference
Answer: A
Q224. An output of the Close Project (or Close Phase) process is:
A. accepted deliverables
B. organizational process asset updates
C. work performance information
D. project management plan updates
Answer: B
Q225. Which quality control technique illustrates the 80/20 principle?
A. Ishikawa diagram
B. Control chart
C. Run chart
D. Pareto chart
Answer: D
Up to date pmi pmi-001 practice exam:
Q226. Which is the correct formula for calculating expected activity cost for three-point estimating?
A. Ce = (C0 + 6Cm + Cp)/4
B. Ce = (6C0 + Cm + Cp)/4
C. Ce = (C0 + 4Cm + Cp)/6
D. Ce = (C0 + C., + 4Cp) / 6
Answer: C
Q227. What cost control technique is used to compare actual project performance to planned or expected performance?
A. Cost aggregation
B. Trend analysis
C. Forecasting
D. Variance analysis
Answer: D
Q228. Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?
A. Schedule Control
B. Activity Definition
C. Schedule Development
D. Activity Resource Estimating
Answer: D
Q229. In the basic communication model, which term refers to the method that is used to convey the message?
A. Decode
B. Encode
C. Medium
D. Noise
Answer: C
Q230. Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
A. Cost management plan.
B. Work performance information.
C. Quality management plan.
D. Work breakdown structure.
Answer: A