★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PMI-001 Exam Dumps (PDF & VCE):
Available on: https://www.certleader.com/PMI-001-dumps.html


Our That experts dedicate in order to keeping the PMI PMI practice questions and also answers up-to-date. You should preserve visit Pass4sure.com regularly to ensure if there are some changes in each of our PMI PMI-001 exam products. And download the latest PMI PMI-001 practice questions timely. You will always be well prepared to the PMI PMI real exam along with our PMI Pdf simulation materials.

2021 Sep pmi-001 questions & answers:

Q321. What process determines which risks might affect the project? 

A. Qualitative risk analysis 

B. Identify Risks 

C. Plan Risk Management 

D. Quantitative risk analysis 

Answer: B 


Q322. Which of the following can be used as an input for Define Scope? 

A. Product analysis 

B. Project charter 

C. Scope baseline 

D. Project scope statement 

Answer: B 


Q323. The purpose of inspection in Perform Quality Control is to keep errors: 

A. in line with a measured degree of conformity. 

B. out of the hands of the customer. 

C. in a specified range of acceptable results. 

D. out of the process. 

Answer: B 


Q324. Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating? 

A. Bottom-up 

B. Parametric 

C. Analogous 

D. Three-point 

Answer: C 


Q325. Most experienced project managers know that: 

A. every project requires the use of all processes in the PMBOK. Guide. 

B. there is no single way to manage a project. 

C. project management techniques are risk free. 

D. there is only one way to manage projects successfully. 

Answer: B 


PMI-001 free exam

Latest pmi-001 dump:

Q326. An input to the Identify Stakeholders process is: 

A. The project management plan. 

B. The stakeholder register. 

C. Procurement documents. 

D. Stakeholder analysis. 

Answer: C 


Q327. Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique? 

A. Expert judgment 

B. Forecasting methods 

C. Earned value management 

D. Analytical techniques 

Answer: D 


Q328. An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as: 

A. Forecasting, 

B. Brainstorming. 

C. Historical databases. 

D. Cost of quality. 

Answer: D 


Q329. Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference? 

A. Compromising 

B. Collaborating 

C. Smoothing 

D. Problem Solving 

Answer: C 


Q330. Which of the following is an input to Develop Human Resource Plan? 

A. Team performance assessment 

B. Roles and responsibilities 

C. Staffing management plan 

D. Enterprise environmental factors 

Answer: D