Q291. The process of developing a detailed description of the project and product is known as:
A. Create WBS.
B. Verify Scope.
C. Collect Requirements.
D. Define Scope.
Answer: D
Q292. Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
A. Estimate Costs
B. Estimate Activity Resources
C. Control Costs
D. Determine Budget
Answer: B
Q293. The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?
A. Initiating
B. Planning
C. Executing
D. Monitoring and Controlling
Answer: B
Q294. What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
A. 0.45
B. 0.56
C. 0.70
D. 1.36
Answer: C
Q295. Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?
A. Inspection
B. Quality audits
C. Design of experiments
D. Root cause analysis
Answer: D
Renewal examcollection pmi-001:
Q296. When sequencing activities, what does the common acronym FF stand for?
A. Fixed Fee
B. Free Float
C. Fixed Finish
D. Finish-to-Finish
Answer: D
Q297. What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?
A. 0.03
B. 0.06
C. 0.10
D. 0.50
Answer: B
Q298. Which tool or technique is used to manage change requests and the resulting decisions?
A. Change control tools
B. Expert judgment
C. Delphi technique
D. Change log
Answer: A
Q299. The Perform Quality Assurance process occurs in which Process Group?
A. Executing
B. Monitoring and Controlling
C. Initiating
D. Planning
Answer: A
Q300. At the end of the project, what will be the value of SV?
A. Positive
B. Zero
C. Negative
D. Greater than one