Q71. Funding limit reconciliation is a tool and technique of which Project Cost Management process? 

A. Estimate Costs 

B. Control Costs 

C. Plan Cost Management 

D. Determine Budget 

Answer: D 


Q72. Which of the following is an example of the simplest fixed-price contract? 

A. Purchase requisition 

B. Purchase order 

C. Verbal agreement 

D. Request for quote 

Answer: B 


Q73. At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create? 

A. Result 

B. Product 

C. Service 

D. Improvement 

Answer: A 


Q74. Which of the following are three inputs to the risk register? 

A. Risk register updates, stakeholder register, and quality management plan 

B. Communication management plan, enterprise environmental factors, and activity duration estimates 

C. Risk management plan, activity cost estimates, and project documents 

D. Project scope statement, organizational process assets, and scope baseline 

Answer: C 


Q75. What is a tool and technique used in the Develop Project Management Plan process? 

A. Project management information system (PMIS) 

B. Project charter 

C. Quality assurance 

D. Expert judgment 

Answer: D 


PMI-001 simulations

Leading pmi-001 pdf:

Q76. A weighting system is a tool for which area of procurement? 

A. Plan contracting 

B. Request seller responses 

C. Select sellers 

D. Plan purchase and acquisition 

Answer: C 


Q77. A tool and technique used during the Create WBS process is: 

A. decomposition 

B. expert judgment 

C. inspection 

D. variance analysis 

Answer: A 


Q78. Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project? 

A. Issue log 

B. Change log 

C. Expert judgment 

D. Change requests 

Answer: B 


Q79. Which of the following consists of the detailed project scope statement and its associatedWBSand WBSdictionary? 

A. Scope plan 

B. Product scope 

C. Scope management plan 

D. Scope baseline 

Answer: D 


Q80. When are deliverables accepted or not accepted? 

A. When the project is initiated 

B. As an output of the scope verification process 

C. When the project is closing 

D. In the contract closure process 

Answer: B