Q631. Decomposition, rolling wave planning, and templates are all tools and techniques for which of the following? 

A. Define Activities 

B. Estimate Activity Durations 

C. Develop Schedule 

D. Sequence Activities 

Answer: A 


Q632. The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is: 

A. Acquire Project Team. 

B. Plan Human Resource Management. 

C. Manage Project Team. 

D. Develop Project Team. 

Answer: A 


Q633. Soft logic is also known as what type of dependency? 

A. External 

B. Discretionary 

C. Mandatory 

D. Internal 

Answer: B 


Q634. Which baselines make up the performance measurement baseline? 

A. Scope baseline, cost baseline, and schedule baseline 

B. Scope baseline, project management baseline, and quality baseline 

C. Cost baseline, schedule baseline, and risk baseline 

D. Cost baseline, project management baseline, and schedule baseline 

Answer: A 


Q635. Which document describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results? 

A. Procurement management plan 

B. Procurement statement of work 

C. Request for proposal 

D. Request for quote 

Answer: B 


PMI-001 test preparation

Down to date pmi-001 testking torrent:

Q636. A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is: 

A. Adaptive 

B. Predictive 

C. Incremental 

D. Iterative 

Answer: B 


Q637. Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them? 

A. Project sponsor and project manager 

B. Project sponsor and functional manager 

C. Project manager and project team 

D. Project team and functional manager 

Answer: C 


Q638. Which of the following is an output from Control Scope? 

A. Change requests 

B. Variance analysis 

C. Accepted deliverables 

D. Requirements documentation 

Answer: A 


Q639. For any given project, the project manager, in collaboration with the project team, is responsible for: 

A. Applying knowledge, skills, and processes uniformly. 

B. Informing the project sponsor about which processes are going to be used. 

C. Tailoring the processes to fit the abilities of the organization. 

D. Determining which particular processes are appropriate. 

Answer: D 


Q640. The process of prioritizing risks for further analysis or action is known as: 

A. Plan Risk Management. 

B. Plan Risk Responses. 

C. Perform Qualitative Risk Analysis. 

D. Perform Quantitative Risk Analysis. 

Answer: C