The PMI-001 computer software of Testking can easily check a testee whether to learn the particular Project Management Professional information securely and real solutions. The Testking PMI-001 items are contain multiple select. Applicant can choose various package deal items for your PMI-001 pdf or perhaps PMI-001 vce computer software according to their very own understand with the PMI-001 scenario.

2021 Oct pmi pmi-001 practice exam:

Q231. What is the minimum a project schedule must include? 

A. Variance analysis 

B. A planned start date and a planned finish date for each schedule activity 

C. A critical path diagram 

D. Critical chain analysis 

Answer: B 


Q232. Which Process Group includes the Manage Stakeholder Engagement process? 

A. Executing 

B. Planning 

C. Monitoring and Controlling 

D. Initiating 

Answer: C 


Q233. Based on the following metrics: EV=$20,000, AC=$22,000, and PV=$28,000, what is the project CV? 

A. -8000 

B. -2000 

C. 2000 

D. 8000 

Answer: B 


Q234. Which technique is utilized in the Schedule Control process? 

A. Performance Measure 

B. Baseline Schedule 

C. Schedule Comparison 

D. Variance Analysis 

Answer: D 


Q235. What are the Project Procurement Management processes? 

A. Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements 

B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements 

C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements 

D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements 

Answer: C 


PMI-001 pdf exam

Renovate testking pmi-001 download:

Q236. Which enterprise environmental factors are considered during cost estimating? 

A. Marketplace conditions and commercial databases 

B. Marketplace conditions and company structure 

C. Commercial databases and company structure 

D. Existing human resources and market place conditions 

Answer: A 


Q237. Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope? 

A. Activity network diagrams 

B. Affinity diagrams 

C. Matrix diagrams 

D. Interrelationship digraphs 

Answer: B 


Q238. Which of the following is a project constraint? 

A. Twenty-five percent staff turnover is expected. 

B. The technology to be used is cutting-edge. 

C. Project leadership may change due to volatile political environment. 

D. The product is needed in 250 days. 

Answer: D 


Q239. In a weak matrix, the project managers role is: 

A. part-time 

B. full-time 

C. occasional 

D. unlimited 

Answer: A 


Q240. The traditional organization chart structure that can be used to show positions and relationships in a graphic top-down format is called a: 

A. Responsible, accountable, consult, and inform (RACI) chart. 

B. Matrix-based chart. 

C. Human resource chart. 

D. Hierarchical-type chart. 

Answer: D