It is more faster and easier to pass the PMI PMI-001 exam by using Top Quality PMI Project Management Professional questuins and answers. Immediate access to the Up to date PMI-001 Exam and find the same core area PMI-001 questions with professionally verified answers, then PASS your exam with a high score now.

2021 Oct testking pmi-001:

Q131. The following chart contains information about the tasks in a project. 

Based on the chart, what is the schedulevariance (SV) for Task 8? 

A. -2,000 

B. -1,000 

C. 1,000 

D. 2,000 

Answer:


Q132. Which schedule network analysis technique modifies the project schedule to account for limited resources? 

A. Human resource planning 

B. Fast tracking 

C. Critical chain method 

D. Rolling wave planning 

Answer:


Q133. Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work days. What should be your concern? 

A. There is a cost under run. 

B. There is a cost overrun. 

C. May not meet deadline. 

D. The project is 20 days behind schedule. 

Answer:


Q134. Which of the following is an output of Close Procurements? 

A. Accepted deliverables 

B. Organizational process assets updates 

C. Managing stakeholder expectations 

D. Performance reports 

Answer:


Q135. What is Project Portfolio Management? 

A. Management of a project by dividing the project into more manageable sub-projects. 

B. Management of a project by utilizing a portfolio of general management skills, such as planning, organizing, staffing, executing and controlling. 

C. Management of all projects undertaken by a company. 

D. Management of a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives. 

Answer:


Renew pmi pmi-001 practice exam:

Q136. Which is an enterprise environmental factor? 

A. Marketplace conditions 

B. Policies and procedures 

C. Project files from previous projects 

D. Lessons learned from previous projects 

Answer:


Q137. Which characteristic is unique to project work and does not apply to operational work? 

A. Performed by individuals 

B. Limited by constraints 

C. Temporary 

D. Performed to achieve organizational objectives 

Answer:


Q138. Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a: 

A. portfolio 

B. program 

C. selection 

D. sub portfolio 

Answer:


Q139. An input required in Define Scope is an organizational: 

A. structure. 

B. process asset. 

C. matrix. 

D. breakdown structure. 

Answer:


Q140. Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity? 

A. Project document updates 

B. Activity list 

C. Activity attributes 

D. Project calendars 