The PMI-001 exam will be the first as well as necessary step to get your PMI PMI certification. The PMI-001 genuine exam tests a candidate?¡¥s potential and skills in genuine implementation. You can get the PMI PMI-001 online course in order to prepare your PMI exam. You can also take a quiz just before buy your PMI PMI products. Nonetheless, its tough for you in order to choose a new proper PMI PMI-001 training materials due to the several varieties of PMI PMI exam questions and answers from the market. We all are proud in the passing ratio. Its our own honor and duty in order to offer a person the best support. Customer help is online at anytime, please make contact with us and express your questions or suggestions and suggestions. Your satisfaction is our own perpetual objective.

2021 Aug testking pmi-001:

Q241. What is the lowest level in the Work Breakdown Structure called? 

A. Work Packages 

B. Activities 

C. Schedules 

D. Tasks 

Answer: A 


Q242. Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within: 

A. project documents updates. 

B. project management plan updates. 

C. change requests. 

D. work performance information. 

Answer: D 


Q243. During which process does the project team receive bids and proposals? 

A. Conduct Procurements 

B. Plan Procurements 

C. Estimate Costs 

D. Control Budget 

Answer: A 


Q244. Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric? 

A. Cost variance (CV) 

B. Cost performance index (CPI) 

C. Budget at completion (BAC) 

D. Variance at completion (VAC) 

Answer: B 


Q245. Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance? 

A. Histogram 

B. Quality audits 

C. Benchmarking 

D. Performance measurement analysis 

Answer: C 


PMI-001 exam topics

Far out pmi-001 testking torrent:

Q246. An input of the Create WBS process is: 

A. requirements documentation. 

B. scope baseline. 

C. project charter. 

D. validated deliverables. 

Answer: A 


Q247. Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan? 

A. Direct and Manage Project Work 

B. Develop Project Management Plan 

C. Plan Quality Management 

D. Monitor and Control Project Work 

Answer: B 


Q248. Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties? 

A. Teaming 

B. Collective bargaining 

C. Sharing 

D. Working 

Answer: A 


Q249. In which Process Group are lessons learned documented? 

A. Planning 

B. Closing 

C. Executing 

D. Initiating 

Answer: B 


Q250. Using the following data, what is the Schedule Performance Index (SPI)? 

EV= $500 PV= $750 AC= $1000 BAC= $1200 

A. 0.67 

B. 1.5 

C. 0.75 

D. 0.5 

Answer: A