Q401. Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV? 

A. -8000 

B. -2000 

C. 2000 

D. 8000 

Answer:


Q402. Which is used to solicit proposals from prospective sellers? 

A. Procurement statement of work 

B. Resource calendars 

C. Procurement document 

D. Independent estimates 

Answer:


Q403. Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations? 

A. Mandatory 

B. Discretionary 

C. Internal 

D. External 

Answer:

17. During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives? 

A. Monitor and Control Project Work 

B. Perform Quality Assurance 

C. Close Project or Phase 

D. Control Scope 

Answer:


Q404. Which of the following tools and techniques is used in the Verify Scope process? 

A. Inspection 

B. Variance analysis 

C. Expert judgment 

D. Decomposition 

Answer:


Q405. Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project? 

A. Define Activities 

B. Direct and Manage Project Work 

C. Develop Project Management Plan 

D. Develop Project Charter 

Answer:


Rebirth examcollection pmi-001:

Q406. Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of: 

A. Earned value management. 

B. Enterprise environmental factors. 

C. Organizational process assets. 

D. Work performance information. 

Answer:


Q407. Which of the following is an output of the Define Activities process? 

A. Activity list 

B. Project plan 

C. Activity duration estimates 

D. Project schedule 

Answer:


Q408. During what process is the quality policy determined? A. Initiating 

B. Executing 

C. Planning 

D. Controlling 

Answer:


Q409. "Tailoring" is defined as the: 

A. effort of addressing each process to determine which are appropriate and their appropriate degree of rigor. 

B. act of creating a project team with the specialized skills required to produce a required product or service. 

C. action taken to bring a defective or nonconforming component into compliance with requirements or specifications. 

D. adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope. 

Answer:


Q410. Which change request is an intentional activity that realigns the performance of the project work with the project management plan? 

A. Update 

B. Preventive action 

C. Defect repair 

D. Corrective action 

Answer: