Pass4sure offers free demo for PK0-003 exam. "CompTIA Project+ (2009)", also known as PK0-003 exam, is a CompTIA Certification. This set of posts, Passing the CompTIA PK0-003 exam, will help you answer those questions. The PK0-003 Questions & Answers covers all the knowledge points of the real exam. 100% real CompTIA PK0-003 exams and revised by experts!
Q41. - (Topic 2)
The WBS is an input for which of the following activities?
A. Schedule planning and budget planning
B. Schedule planning and scope planning
C. Budget planning and project charter
D. Scope planning and budget planning
Answer: A
Q42. - (Topic 1)
A company is replacing their file server with a new one. During the data migration, the old file server experiences critical hardware failure. The data migration cannot continue until the hardware is replaced. This repair will put the project behind schedule by a week. Which of the following actions should the project manager do FIRST?
A. Prepare performance report
B. Manage the issue
C. Schedule a meeting
D. Update communication plan
Answer: B
Q43. - (Topic 2)
Which of the following project charter components will identify significant events leading to completion of the project?
A. Cost estimates
B. Milestones
C. Objectives
D. Assumptions
Answer: B
Q44. - (Topic 1)
A project has been running for four months. The planned value to this point is $100,000. The actual cost is an average of $30,000 per month. Earned value is $90,000. Which of the following is the current cost performance index?
A. 0.75
B. 1.25
C. $20,000 over budget
D. Not enough detail to determine
Answer: A
Q45. - (Topic 3)
A project manager is leading a training session relating to the software development lifecycle in use at the organization. Several of the developers report that the CCB is unnecessary and that it simply delays development efforts on critical projects. Which of the following would be the BEST explanation for the purpose of the CCB?
A. The CCB ensures that changes have been approved by the end user prior to analysis.
B. The CCB ensures that stakeholders are aware of the impact of the change on the project budget.
C. The CCB ensures that properly analyzed and approved items are submitted for implementation.
D. The CCB ensures that implementations are documented and budgeted by the development team.
Answer: C
Q46. - (Topic 2)
A project involves outsourcing multiple parts of the software application to developers around the world. Which of the following is MOST likely to impact meeting attendance?
A. Time zone differences
B. Cultural differences
C. Language barriers
D. Technology barriers
Answer: A
Q47. - (Topic 1)
Which of the following is a component of a performance evaluation for an individual?
A. Resource utilization
B. Role assessment
C. Scope management
D. Variance management
Answer: B
Q48. - (Topic 2)
A key stakeholder asks the project manager to change the color of the envelope that will be used as part of the project deliverable. This is a minor change that will require the project manager to do which of the following FIRST?
A. Enter the change in the change log.
B. Provide a budget estimate.
C. Implement the change.
D. Analyze the impact of the change.
Answer: A
Q49. - (Topic 3)
Once all of the requirements have been gathered and development is ready to begin, which of the following should be the project manager's NEXT step?
A. Create a project plan
B. Update the scope document
C. Obtain approval
D. Perform fast tracking
Answer: C
Q50. - (Topic 3)
Construction on a new building has been delayed by two weeks due to rain. With no additional resources or budget available, the project manager must implement some type of resource leveling in hopes of completing the project on time. Which of the following is the project manager MOST likely to do?
A. Complete tasks originally scheduled in sequence to be done in parallel
B. Reduce the scope of the planned deliverable
C. Increase the number of staff working on the remaining tasks
D. Increase the daily work hours of the personnel working on the project
Answer: A