★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions
Free Instant Download NEW PK0-003 Exam Dumps (PDF & VCE):
Available on:
https://www.certleader.com/PK0-003-dumps.html
Want to know Exambible PK0-003 Exam practice test features? Want to lear more about CompTIA CompTIA Project+ (2009) certification experience? Study Free CompTIA PK0-003 answers to Up to the immediate present PK0-003 questions at Exambible. Gat a success with an absolute guarantee to pass CompTIA PK0-003 (CompTIA Project+ (2009)) test on your first attempt.
Q91. - (Topic 2)
A project manager is notified that a task on the project has zero float. Which of the following can be derived about the task?
A. The task is on the critical path.
B. The task is being performed early.
C. The task failed a quality audit.
D. The task is behind schedule.
Answer: A
Q92. - (Topic 2)
A project consists of completing a technical refresh of a datacenter. The existing network infrastructure does not support the new network cards. A conflict arises with the technical refresh schedule because it now depends on an upgrade to the network infrastructure. The network infrastructure team did not plan and does not have the budget to upgrade until two years from now. The project manager talks to the stakeholders to explain that the project cannot continue until the network infrastructure is upgraded. The stakeholders agree to pay for the network infrastructure upgrade and to allow the schedule to slip. Which of the following conflict resolution techniques does this scenario describe?
A. Forcing
B. Negotiating
C. Smoothing
D. Avoiding
Answer: A
Q93. - (Topic 2)
When working on the monitoring and controlling phase of the project lifecycle, which of the following activities would occur?
A. Third-party auditors will evaluate documentation.
B. Team members will participate in lessons learned events.
C. Project manager will direct and manage work tasks.
D. Senior management will review the project scope document.
Answer: A
Q94. - (Topic 1)
Which of the following describes the purpose of a war room on a project?
A. It is a space where project managers negotiate for project team resources
B. It is a wireless access room which allows for strong Internet connectivity
C. It is a location set aside for project use
D. It is a room used to send conflicting team members to work out conflicts
Answer: C
Q95. - (Topic 1)
The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?
A. Cost performance index
B. Risk mitigation
C. Schedule variance
D. Cost variance
Answer: C
Q96. - (Topic 2)
Which of the following should be updated after a change request has been approved?
A. Risk register
B. Project charter
C. Issues log
D. Project scope documents
Answer: D
Q97. - (Topic 3)
The project manager informs the team that the client has approved a change in the direction of the project. Which of the following tasks should the project manager perform NEXT?
A. Update cost and schedule baselines
B. Schedule meetings based on the project schedule
C. Review the communications plan and follow the steps
D. Establish project quality by using the quality management metrics
Answer: A
Q98. - (Topic 2)
Which of the following is contained in the WBS dictionary?
A. Responsibility matrix
B. Key performance indicators
C. Account identifiers
D. Project stakeholders
Answer: C
Q99. - (Topic 1)
A system has been released to a pilot group of users and a call center will be maintained for the next 30 days for support. The business line will not be ready to support the new setup for at least 60 days. Which of the following should be reviewed to ensure a smooth handoff?
A. Converting the project team to an operational team
B. The transition dates, and make adjustments
C. Training opportunities to allow the business to assume support within the next 30 days
D. Giving the business line as much time as needed to support the new system
Answer: B
Q100. - (Topic 3)
Approval from which of the following entities is required to make a project charter valid?
A. Accounting
B. Project sponsor
C. Developer
D. Legal
Answer: B