Want to know Actualtests PK0-003 Exam practice test features? Want to lear more about CompTIA CompTIA Project+ (2009) certification experience? Study Virtual CompTIA PK0-003 answers to Far out PK0-003 questions at Actualtests. Gat a success with an absolute guarantee to pass CompTIA PK0-003 (CompTIA Project+ (2009)) test on your first attempt.

2021 Apr PK0-003 practice

Q141. - (Topic 3) 

A customer of a project states that the timeline for user acceptance testing, noted in the kickoff meeting, has already passed and testing has yet to start. After annual holiday leave has been approved within the customer's department, it was announced that staff would be needed for user acceptance testing. How could this issue have been avoided? 

A. Proactive communication should have been kept with Stakeholders 

B. Project manager should have approved all annual leave 

C. Scope Management should have been implemented 

D. Change management procedures should have been followed 

Answer:


Q142. - (Topic 3) 

A project manager is finalizing the WBS when the resource manager provides a list of project team members. Which of the following is the FIRST thing the project manager should do? 

A. Obtain outsourcing approval 

B. Conduct a kick-off meeting 

C. Interview resources for skill sets 

D. Assign resources to all tasks 

Answer:


Q143. - (Topic 1) 

Which of the following describes the total amount of money approved for spending on a project? 

A. VAC 

B. BAC 

C. ETC 

D. EAC 

Answer:


Q144. - (Topic 3) 

Which of the following cost estimates are included in a project charter? 

A. Analogous 

B. High-level 

C. Bottom-up 

D. Parametric 

Answer:


Q145. - (Topic 2) 

Which of the following are valid conflict resolution techniques? 

A. Smoothing, forcing, compromising, avoiding, and influencing 

B. Smoothing, forcing, considering, avoiding, and negotiating 

C. Smoothing, enforcing, compromising, avoiding, and negotiating 

D. Smoothing, forcing, compromising, avoiding, and negotiating 

Answer:


Updated PK0-003 vce:

Q146. - (Topic 3) 

Which of the following would MOST likely be found in the quality management plan? (Select TWO). 

A. Resource quality policies 

B. Quality assurance process description 

C. Risk register 

D. Frequency of quality measurement 

E. Manufacturing specification details 

F. Quality cost calculations 

Answer: B,D 


Q147. - (Topic 2) 

Which of the following cost estimating techniques relies on the actual costs of previously completed projects that are similar in nature? 

A. Bottom-up 

B. Three-point 

C. Analogous 

D. Parametric 

Answer:


Q148. - (Topic 3) 

A project manager notices that several team members are not performing at the rate that they were originally expected. The project manager should: 

A. schedule a meeting. 

B. fast track the project. 

C. evaluate triple constraint impact. 

D. identify the variances. 

Answer:


Q149. - (Topic 1) 

Which of the following components of the project charter is used to help determine the project’s communication needs? 

A. Stakeholder identification 

B. Project objectives 

C. Problem statement 

D. Key deliverables 

Answer:


Q150. - (Topic 1) 

A project manager schedules a weekly meeting to review the project schedule. The project manager is looking for an easy way to see the project tasks and review areas where tasks may overlap and are dependent on others. Which of the following would provide the project manager with the BEST project view? 

A. PERT 

B. Pareto 

C. CPM 

D. Gantt 