Q101. If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months, what is the probability that this risk event will occur during the fourth month of the project?
A. Less than 1 percent
B. 20 percent
C. 60 percent
D. 80 percent
Answer: B
Q102. The role of the _____ can be invaluable in problem solving.
A. dominator
B. devils advocate
C. recognition seeker or dominator
D. topic jumper
E. recognition seeker
Answer: B
Q103. Who is responsible for issuing the project charter?
A. The project sponsor
B. The senior Project Manager
C. The project team
D. The project manager
Answer: A
Q104. The positive value of conflict is underestimated. Properly managed, conflict is a valuable tool, particularly when
A. A diversion is needed
B. Conflict may cause a loss of status or position power
C. Conflictive situations are in their early stages and emotional involvement is low
D. Conflictive situations are in their late stages and emotional involvement is high
Answer: C
Q105. Placing many or all of the most active project team members in the same physical location to enhance their ability to perform as a team is called which of the following?
A. Team training
B. Co-location
C. Team location
D. Organization training
Answer: B
Most recent ms pmp:
Q106. How is scheduled variance calculated using the earned value technique?
A. EV less AC
B. AC less PV
C. EV less PV
D. AC less EV
Answer: C
Q107. What are the performance measurements for the Schedule Control process?
A. SV (EV - PV) and SPI (EV ?PV)
B. SV (PV - EV) and SPI (PV ?EV)
C. SV (EV - BAC) and SPI (EV ?BAC)
D. SV (EV - AC) and SPI (EV ?AC)
Answer: A
Q108. A team member is not performing well on the project because she is inexperienced in system development work. There is no one else available who is better qualified to do the work. What is the BEST solution for the project manager?
A. Consult with the functional manager to determine project completion incentives for the team member.
B. Obtain a new resource more skilled in development work.
C. Arrange for the team member to get training.
D. Allocate some of the project schedule reserve.
Answer: C
Q109. Formal written correspondence is mandated in which of the following situations:
A. Client requests additional work not covered under contract
B. None of the other alternatives apply
C. Both 1) Client requests additional work not covered under contract, and 2) Project manager calls a meeting.
D. Project manager calls a meeting
E. Product undergoes casual in-house testing
Answer: A
Q110. How many knowledge areas are there according to PMBOK Guide?
A. 5
B. 8
C. 9
D. 12
Answer: C