Q551. Plan Schedule Management is a process in which Knowledge Area? 

A. Project Scope Management 

B. Project Human Resource Management 

C. Project Integration Management 

D. Project Time Management 

Answer: D 


Q552. Sensitivity analysis is typically displayed as a/an: 

A. Decision tree diagram. 

B. Tornado diagram. 

C. Pareto diagram. 

D. Ishikawa diagram. 

Answer: B 


Q553. Projects can be divided into phases to provide better management control. Collectively, what are these phases known as? 

A. Complete project phase 

B. Project life 

C. The project life cycle 

D. Project cycle 

Answer: C 


Q554. Which of the following is a component of three-point estimates? 

A. Probabilistic 

B. Most likely 

C. Expected 

D. Anticipated 

Answer: B 


Q555. Which tool or technique measures performance of the project as it moves from project initiation through project closure? 

A. Resource leveling 

B. Parametric measuring 

C. Pareto chart 

D. Earned value 

Answer: D 


PMI-001 training

Replace pmi-001 testking torrent:

Q556. A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date? 

A. US$S000 

B. US$9500 

C. US$10,000 

D. US$12,500 

Answer: D 


Q557. Which input will be used when tasked with developing the human resource plan? 

A. Project management plan 

B. Activity resource requirements 

C. Resource calendar 

D. Project staff assignments 

Answer: B 


Q558. An output of the Develop Project Team process is: 

A. change requests 

B. team performance assessments 

C. project staff assignments 

D. project documents updates 

Answer: B 


Q559. Which tool and technique of quality planning involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance? 

A. Histogram 

B. Quality audits 

C. Benchmarking 

D. Performance measurement analysis 

Answer: C 


Q560. Funding limit reconciliation is a tool and technique used in which process? 

A. Control Costs 

B. Determine Budget 

C. Estimate Costs 

D. Control Budget 

Answer: B