It is more faster and easier to pass the PMI PMI-001 exam by using Approved PMI Project Management Professional questuins and answers. Immediate access to the Rebirth PMI-001 Exam and find the same core area PMI-001 questions with professionally verified answers, then PASS your exam with a high score now.

2021 Sep testking pmi-001 download:

Q441. A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor? 

A. Urgent information need 

B. Sensitivity of information 

C. Project environment 

D. Ease of use 

Answer: C 


Q442. What do composite organizations involve? 

A. Functional and project managers 

B. Functional managers only 

C. Project managers only 

D. Technical managers and project managers 

Answer: A 


Q443. Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process? 

A. Control Schedule 

B. Define Activities 

C. Develop Schedule 

D. Estimate Activity Resources 

Answer: D 


Q444. Which of the following methods is a project selection technique? 

A. Flowcharting 

B. Earned value 

C. Cost-benefit analysis 

D. Pareto analysis 

Answer: C 


Q445. Co-location is a tool and technique of: 

A. Develop Human Resource Plan. 

B. Manage Project Team. 

C. Develop Project Team. 

D. Acquire Project Team. 

Answer: C 


PMI-001 exam question

Update phytomedics pmi-001:

Q446. Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties? 

A. Critical path method 

B. Critical chain method 

C. Resource leveling 

D. Schedule network analysis 

Answer: B 


Q447. What is the number of stakeholders, if the project has 28 potential communication channels? 

A. 7 

B. 8 

C. 14 

D. 16 

Answer: B 


Q448. Sending letters, memos, reports, emails, and faxes to share information is an example of 

which type of communication? 

A. Direct 

B. Interactive 

C. Pull 

D. Push 

Answer: D 


Q449. Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project? 

A. Project Risk Management 

B. Project Human Resource Management 

C. Project Scope Management 

D. Project Stakeholder Management 

Answer: D 


Q450. Which document describes the necessary information to determine if a project is worth the required investment? 

A. Cost baseline 

B. Service level agreement 

C. Memorandum of understanding 

D. Business case 

Answer: D