It is more faster and easier to pass the PMI PMI-001 exam by using Tested PMI Project Management Professional questuins and answers. Immediate access to the Refresh PMI-001 Exam and find the same core area PMI-001 questions with professionally verified answers, then PASS your exam with a high score now.

2021 Jul pmi-001 pdf:

Q161. In the Develop Project Team process, which of the following is identified as a critical factor 

for a project's success? 

A. Team meetings 

B. Subcontracting teams 

C. Virtual teams 

D. Teamwork 

Answer: D 


Q162. A procurement management plan is a subsidiary of which other type of plan? 

A. Resource plan 

B. Project management plan 

C. Cost control plan 

D. Expected monetary value plan 

Answer: B 


Q163. The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project? 

A. $800 

B. $1000 

C. $1250 

D. $1800 

Answer: A 


Q164. A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document? 

A. Work breakdown structure 

B. Requirements document 

C. Project charter 

D. Project management plan 

Answer: C 


Q165. Inputs to the Plan Risk Management process include the: 

A. cost management plan. 

B. risk management plan, 

C. activity list, 

D. risk register. 

Answer: A 


PMI-001 practice

Improved pmi pmi-001 practice exam:

Q166. Which is an output from Distribute Information? 

A. Earned value analysis 

B. Trend analysis 

C. Project records 

D. Performance reviews 

Answer: C 


Q167. The Identify Stakeholders process is found in which Process Group? 

A. Initiating 

B. Monitoring and Controlling 

C. Planning 

D. Executing 

Answer: A 


Q168. Which of the following forecasting methods uses historical data as the basis for estimating future outcomes? 

A. Time series 

B. Judgmental 

C. Econometric 

D. Simulation 

Answer: A 


Q169. Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of: 

A. influencing 

B. leadership 

C. motivation 

D. coaching 

Answer: A 


Q170. The process of obtaining seller responses, selecting a seller, and awarding a contract is called: 

A. Close Procurements. 

B. Control Procurements. 

C. Plan Procurements. 

D. Conduct Procurements. 

Answer: D