It is more faster and easier to pass the PMI PMI-001 exam by using Tested PMI Project Management Professional questuins and answers. Immediate access to the Refresh PMI-001 Exam and find the same core area PMI-001 questions with professionally verified answers, then PASS your exam with a high score now.
2021 Jul pmi-001 pdf:
Q161. In the Develop Project Team process, which of the following is identified as a critical factor
for a project's success?
A. Team meetings
B. Subcontracting teams
C. Virtual teams
D. Teamwork
Answer: D
Q162. A procurement management plan is a subsidiary of which other type of plan?
A. Resource plan
B. Project management plan
C. Cost control plan
D. Expected monetary value plan
Answer: B
Q163. The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
A. $800
B. $1000
C. $1250
D. $1800
Answer: A
Q164. A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
A. Work breakdown structure
B. Requirements document
C. Project charter
D. Project management plan
Answer: C
Q165. Inputs to the Plan Risk Management process include the:
A. cost management plan.
B. risk management plan,
C. activity list,
D. risk register.
Answer: A
Improved pmi pmi-001 practice exam:
Q166. Which is an output from Distribute Information?
A. Earned value analysis
B. Trend analysis
C. Project records
D. Performance reviews
Answer: C
Q167. The Identify Stakeholders process is found in which Process Group?
A. Initiating
B. Monitoring and Controlling
C. Planning
D. Executing
Answer: A
Q168. Which of the following forecasting methods uses historical data as the basis for estimating future outcomes?
A. Time series
B. Judgmental
C. Econometric
D. Simulation
Answer: A
Q169. Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:
A. influencing
B. leadership
C. motivation
D. coaching
Answer: A
Q170. The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
A. Close Procurements.
B. Control Procurements.
C. Plan Procurements.
D. Conduct Procurements.
Answer: D