Want to know Testking 70-499 Exam practice test features? Want to lear more about Microsoft Recertification for MCSD: Application Lifecycle Management certification experience? Study High quality Microsoft 70-499 answers to Most recent 70-499 questions at Testking. Gat a success with an absolute guarantee to pass Microsoft 70-499 (Recertification for MCSD: Application Lifecycle Management) test on your first attempt.
2021 Aug 70-499 vce
Q41. - (Topic 3)
A development team is attempting to use Scrum as its process framework. You join the team as the new scrum master.
During a meeting, a developer states that his “task is done.”
You need to describe to the team how the word “done” relates to Scrum.
What should you do?
A. The word “done” indicates that code has been approved for release to production.
B. The word “done” indicates that code compiles and has been unit tested.
C. The word “done” indicates that code has been approved through testing and quality assurance.
D. The word “done” must be defined, communicated, and agreed to by the team.
Answer: D
Explanation: The Definition of “Done” is a simple, auditable checklist created by the Development Team. It must be understandable by the Product Owner, the Scrum Master, and any stakeholders.
Professional Scrum Development with Microsoft Visual Studio 2012 p.36
Q42. - (Topic 3)
You are part of a scrum team that needs to identify user stories to complete in the next sprint.
What should the scrum master do?
A. Have the product owner decide which user stories to complete within the sprint.
B. Order the user stories by their story points. Select the top stories based on the team's velocity.
C. Have the team decide which user stories to complete within the sprint.
D. The scrum master should decide which user stories to complete within the sprint.
Answer: C
Q43. - (Topic 3)
You manage a development team by using Microsoft Team Foundation Server (TFS) 2012. The development team is made up of developers with specific skills.
The project you are developing has the following characteristics:
Several external dependencies exist.f
Requirements are well defined and will not change.
If an external dependency on the critical path does not meet a committed to
deadline, the project will be impacted.
The impact should be identified and measured.
... .
You need to select the appropriate tool(s) for managing the project.
What should you do?
A. Use Microsoft Project to manage dependencies and integrate with TFS where needed.
B. Use TFS with the Microsoft Visual Studio Scrum 2.0 project template.
C. Use TFS with the Microsoft Solution Framework (MSF) for Capability Maturity Model Integration (CMMI) Process Improvement 6.0 project template and the Affects link type for managing dependencies.
D. Use TFS with the MSF for Agile Software Development 6.0 process template and the web access task board.
Answer: A
Q44. - (Topic 2)
You are using Microsoft Test Manager (MTM). You are using the Microsoft Solution Framework (MSF) for Agile Software Development process template.
You have created a test plan named Validate_User_Registration that contains test cases for validating new user registrations.
All the user stories for the new user registration feature have been stored as work items in Team Foundation Server 2012.
You need to associate the user registration user stories with the test cases in the Validate_User_Registration test plan.
What should you do?
A. Open the test plan. Use the Add requirements function to add the user registration requirements.
B. Open the test cases. Upload the user registration requirements document as an attachment.
C. Open the test cases. From the Tested User Stories tab, link the test case to the associated user stories.
D. Open the test plan. Link the user registration requirements document to the test plan.
Answer: C
Q45. - (Topic 3)
You have a web application that should be automatically deployed to a standard environment, including two staging web servers. You USE the LabDefaultTemplate.11.xaml build process template for your build definition.
You plan to run automated tests on the application as part of the build process.
You need to configure the build definition to deploy the application.
What should you do?
A. Create deployment scripts to perform the deployment. In the Deploy section of the build process template, select Deploy the build and specify the computer names and the scripts to be executed.
B. In the build definition, specify the MS Build arguments as /p:DeployOnBuild=true;DeployTargetPackage.
C. Define separate drop folders for each web server.
D. In the build definition, specify Private Drop Location. Indicate the scripts to be executed after a successful build.
Answer: A
Update 70-499 test question:
Q46. DRAG DROP - (Topic 2)
You are using Microsoft Test Manager (MTM).
Your company would like to support the Windows Server 2008 operating system for the application being tested.
You need to add Windows Server 2008 as a new value to the operating system configuration variable.
What should you do? (To answer, move the four appropriate actions from the list of actions to the answer area and arrange them in the correct order.)
Answer:
Q47. - (Topic 2)
You are using Microsoft Test Manager (MTM).
Your company no longer supports a particular configuration for the application under test.
You need to ensure that the test configuration is unavailable as an option in a test plan.
Which state should you assign to the test configuration?
A. Closed
B. Inactive
C. Disabled
D. Idle
Answer: B
Q48. DRAG DROP - (Topic 2)
You are using Microsoft Test Manager (MTM) to perform exploratory testing.
You need to test a Windows Store application.
You need to configure the connection to the remote device running the Windows Store
application.
What should you do? (To answer, move the three appropriate actions from the list of actions to the answer area and arrange them in the correct order.)
Answer:
Q49. - (Topic 1)
Your network environment includes a Team Foundation Server (TFS) 2012 named TFS1 that contains two project collections named PC1 and PC2. A build server named Bi is configured with a build controller named C1 and an agent named A1 that runs build definitions created in Pd.
A development team wants to create a gated check-in build definition on PC2.
You need to perform a supported infrastructure enhancement to run PC2 build definitions.
What should you do?
A.
.
Add a new build server (B2).
.
On the B2 build server, migrate controller C1 and install a new controller (C2) that connects to the PC2 project collection.
.
On the Bi build server, configure a second build agent (A2) that uses the C2 controller.
B.
.
Add a new build server (B2).
.
On the B2 build server, install a build controller (C2) that connects to the PC2 project collection.
.
On the B2 build server, configure a second build agent (A2) that uses the C2 controller.
C.
.
On the Bi build server, configure the C1 controller to connect to project collections PC1 and PC2.
.
On the Bi build server, update the Al agent to use controllers C1 and C2.
D.
.
On the Bi build server, configure the C1 controller to connect to project collections PC1 and PC2.
.
On the Bi build server, configure a second build agent (A2) that uses the C2 controller.
Answer: B
Q50. DRAG DROP - (Topic 2)
You are using Microsoft Test Manager (MTM) to manage your testing efforts.
You need to produce a list of manual test runs over the past week.
What should you do? (To answer, move the three appropriate actions from the list of
actions to the answer area and arrange them in the correct order.)
Answer: